Closed horizontal
tank with closed liner
Kentain flexible PVC liners
are designed to make installation a simple, safe and
efficient operation. Totally prefabricated at the factory,
the Kentain liner can usually be installed in two to
three days. Installation of the Kentain liner in horizontal
tanks requires by a Kentain supervisor and /or crew
who are certified for confined space entry.
Preparation of the interior of the tank does not require
expensive downtime and sand blasting. Simply remove
all sharp projections and loose scales on the existing
tank interior.
The prefabricated flexible Kentain liner
is lowered through the manway and spread out with the
top side up. The manway flange is raised to the top
of the tank.
An internal rib cage of plastic hoops and supports is
installed and upon completion of the installation the
liner is visually inspected by the Kentain supervisor.
Downtime is minimized since the tank walls do not have
to be sand blasted.
|