Closed horizontal tank with closed liner

Kentain flexible PVC liners are designed to make installation a simple, safe and efficient operation. Totally prefabricated at the factory, the Kentain liner can usually be installed in two to three days. Installation of the Kentain liner in horizontal tanks requires by a Kentain supervisor and /or crew who are certified for confined space entry.

Preparation of the interior of the tank does not require expensive downtime and sand blasting. Simply remove all sharp projections and loose scales on the existing tank interior.

The prefabricated flexible Kentain liner is lowered through the manway and spread out with the top side up. The manway flange is raised to the top of the tank.

An internal rib cage of plastic hoops and supports is installed and upon completion of the installation the liner is visually inspected by the Kentain supervisor.

Downtime is minimized since the tank walls do not have to be sand blasted.


 